By The Magnolia Standard · November 24, 2026

In August the number on the table was $350 million. On Thursday it was $496 million, for a building sized to 2050.

Montgomery County's architects came back to commissioners on Thursday, November 19, with a bigger justice center and a bigger price. The presentation put the total project cost at an estimated $496 million for a building of about 481,000 square feet, according to Community Impact's report of the workshop.

Nobody voted. It was a workshop, and the point was to get commissioners' reactions to four ways of laying out the building.

What changed since August

The plan the county shelved in August was about 316,000 square feet with 21 courts and a 777-space garage, estimated at $342.3 million and rounded to $350 million. Commissioners did not put it on the November ballot. Judges told them it was already too small, and in September the court asked the architects, Dallas-based BSW Architects, to size the building for the long run and come back with new figures. We covered that history last week.

This is that answer. The new design assumes every elected judge and every associate judge gets a dedicated courtroom. "Our plan that we are going to be talking about and showing you numbers on [is] assuming that each associate judge has a dedicated courtroom as well as every seated elected judge," said Gina Irwin, a BSW principal.

The county uses 17 courtrooms now, with an 18th on the way. The presentation said it needs 23 today and 42 courtrooms plus two specialty court spaces by 2050. Case filings are projected to roughly double, from 34,948 in 2025 to 72,133 in 2050. Courts take up about two-thirds of the planned space.

The four options

All four hold 44 courts. They differ in height and in how many secure parking spaces fit inside:

  • Option A: 13 floors, 52 secure parking spaces
  • Option B: 10 floors, 42 secure parking spaces
  • Option C: 8 floors, 50 secure parking spaces
  • Option D: 10 floors, 46 secure parking spaces

The site in downtown Conroe is the hard part. Closing North San Jacinto Street was floated earlier as a way to give the building room. The architects said Thursday that utilities run under that street, so some options leave them in place and some move them. "Both options can be done. It's a budget decision," said Ryan Mclemore, a BSW vice president. Setbacks on Philip Street and the other sides could run from 20 to 40 feet, he said, and those choices move the cost too.

The jail is part of the backdrop. The presentation described the 40-year-old jail as short on space, with aging systems and delays moving inmates to state prison.

What happens next

Commissioners and the architects agreed BSW will bring more design and cost information, including new options, to the Commissioners Court meeting on Thursday, December 17.

No bond has been called and no way of paying for the building has been picked. If commissioners want it on the May 1, 2027 ballot, Texas law gives them until February 12 to order the election. Any bond would carry a dollar figure, and we would lay out the strongest case on each side before you vote.

The building would go up in Conroe. The bill, if there is one, would reach every property tax statement in the county.

Editor's note on format: We chose straight reporting because this piece records what was presented to commissioners and when they meet next. Whether to build, how big and how to pay are community decisions where reasonable people disagree; if a bond reaches the ballot we will run both sides and let you decide.

Sources: Community Impact, "Montgomery County commissioners discuss new justice center design in workshop", November 23, 2026, for the $496 million estimate, the 481,000 square feet, the courtroom and filing figures, the four options, both quotes, the site and jail notes, and the December 17 follow-up; Community Impact, September 18, 2026, for the earlier 316,000-square-foot plan and the September request; our November 17 story for the $342.3 million figure and the February 12 ordering deadline under Texas Election Code Section 3.005. We did not see the presentation slides; the figures are as reported. Corrections: editor@themagnoliastandard.news.