It's Official: Kresston Elementary. Magnolia ISD Also Approved the First $5.9 Million and Saw Its First Look at the High School Additions.
By The Magnolia Standard · November 20, 2026
We told you Tuesday this would wait for Friday. Here it is: the board voted yes on both items, and the high schools got their first drawings.
Elementary No. 10 has a name. At its regular meeting Monday night, November 16, the Magnolia ISD board of trustees voted to call the school Kresston Elementary, after the Kresston development off FM 1486 where the district bought the site.
The board also approved the first construction package for the school, the item we laid out in last Friday's edition. Community Impact, which covered the meeting, reported both votes.
Magnolia ISD does not stream its board meetings, and its minutes are approved at the following meeting. That is why this report comes four days after the vote and not the next morning.
What the first package pays for
The package goes to B&C Constructors, the district's builder for this campus. The total in the builder's October 30 proposal, attached to the board item, is $5,885,240.42. It covers the work that has to happen before walls go up:
- Structural steel: $4,405,534
- Clearing, grubbing, the building pad and grading: $835,000
- Underground electrical: $232,707
- Stormwater pollution controls: $28,000
- Temporary fencing and temporary facilities: $30,000
- The builder's general conditions and fee: $353,999.43
Steel is the big line. Tim Bruner, the district's executive director of facilities, told the board steel prices have climbed. Compared with a steel package the district bought in 2023, he said, the cost is up an estimated 36 to 37 percent, or about $1 million, according to Community Impact's account.
Community Impact's story printed the steel line as $4.04 million. The builder's proposal in the board packet says $4,405,534, and that is the figure we use. The six lines above add to the package total; the lower number does not.
What comes next for the school
This package is a little more than a tenth of the job. The district has estimated the whole school at about $54 million. The number that sets the real price is the guaranteed maximum price, which the district's schedule puts before the board on February 8, 2027, with construction starting in March. The district says the school opens by August 2028.
It is meant to take pressure off Audubon Elementary, and possibly Williams Elementary.
The high school additions
The same night, architects from PBK showed the board early renderings of the additions the May bond pays for at Magnolia High and Magnolia West High. No vote was taken on them.
The two additions are close to mirror images, the architects said. One design, built twice. Each gets an outdoor courtyard with turf, a covered patio and places to sit, and the courtyard gives students a path to the bus-loading and drop-off areas.
Each campus also gets a multipurpose activity center, bigger than the cafeterias the schools use now for the same jobs. The plan includes mirrors for dance practice and projectors for assemblies and presentations, with room for fine-arts programs.
The renderings were a first look. Costs and a construction schedule for the additions were not part of what Community Impact reported from the meeting.
Sources: Community Impact, November 17, 2026, for the votes on the name and the package, the $54 million estimate, the August 2028 opening and Tim Bruner's steel comments; Community Impact, November 18, 2026 (updated November 19), for the PBK presentation on the high school additions. The Magnolia ISD agenda for the November 16 meeting, posted on BoardBook, and B&C Constructors' October 30, 2026 proposal attached to it, for the package lines and total, the site and the campuses it relieves. Our September 25 story, for the February 8 price vote and the March 2027 start. Corrections: editor@themagnoliastandard.news.